Good morning,
The Contractor Manager at Risk (CMAR) Whiting Turner has submitted the Risk Reserve Request form No. 2 including a lease for the property in which the project trailer will be located.
At this time, we need to determine if there are any legal, ROW or environmental issues, we need to be aware of when our contractor enters to a private property lease like this.
The Risk Reserve Section of the Tropicana Escalators GMP specifications shows the following:
“7. RISK RESERVE
7.1 General. This work shall consist of repairing, rebuilding, replacing, protecting, constructing or reconstruction of any surface or subsurface improvements which are not specified in the Construction Documents provided such work is separately authorized by the