1.0 INTRODUCTION
Building multi storey luxury apartments is essential in the modern world. The population of the world is increasing so it is compulsory to utilize the land wisely.
Constructing apartments would result higher population to accommodate comfortably in a minimum area.
Superb Homes Pvt. Ltd. (S.H.Ltd.), a real estate agent has decided to construct a 6 storey semi luxury type apartments with at least 1400 sqft in size in Church Road, Mattakkuliya.
Modern facilities have been included in the plan in order to fulfill the needs of the families occupying the apartments.
One of the main concerns is to construct with a minimum disruption to the neighboring school. The construction is planned to be completed by October 2015.
The
…show more content…
This could take some extra time in choosing the contractor through competitive tendering. The available time to complete the project is only about 8 months so there can be a delay.
Carrying out the design and construction process separately could cost more. It could be harder to complete the project within the given cost.
Quality could be slightly better but it is not possible to afford too much time in achieving that quality because the duration of the project is short.
The chances for disputes are high in traditional procurement because too parties are involved. If there are any defective works it could be difficult to identify whether it is a construction defect or a defect relevant to the design. This would raise the arguments and could lead to disputes. It usually takes a longer time to resolve a dispute so this would end up in delay of the project.
If the contractor is not involved in the design process this could sometimes lead to “buildability” problems (the contractor would have less understanding about the design).
Management procurement is inappropriate in this project for the following
…show more content…
According to this project there is no need for an early completion.
There is also a risk of late completion because there are many subcontractors involved so if one or many fails to complete their jobs within the allocated time it could extent the project period.
In management procurement the work is done by hiring experts. This could be more expensive comparing to any other procurement types. The budget of the project is fixed at the start. This procurement type is not suitable because the total cost cannot be decided until the completion of the project.
Quality could be high in comparing to other procurement types but it is not possible to afford too much for quality in this project. Quality is not only the criteria to consider.
In management procurement the works are subcontracted to many subcontractors so this increases the possibilities for the disputes.
It is not necessary to have many subcontractors for a project such as construction of apartments. It could be more logical for a project with higher budget or for a complex
SUPERTECH Limited has made its name big in the real estate industry in India. The company sets new trends of engineering finesse in the modern international situation touching the skylines of brilliance. Supertech has introduced many lavish and premium residential projects all across NCR Delhi. Recently, the company has just launched one of its most awaited residential project ROMANO - having the theme of roman lifestyle. Supertech Romano fulfills your desires of living your life in royal luxury. Supertech Romano have the theme of Roman style. Gracious and also symbolic. This project is brilliantly designed, complex is integrated features of a higher level of environmentally responsible design. Supertech Romano have an exceptional level of solaces, services and extravagance, live above everyone else. The structure in Romano brilliantly constructed keeping in mind the natural ventilation system, use of renewable energy through solar system and usage of other recycled material. Supertech Romano is an except...
By doing so the client will either end up with a structural issue that may be a safety problem in the future or at least an unexpected cost for structural design. Either was their interest were not
My supervisor did most of the dealing with contracts. Other than learning that building management/owner will draft it and we sign it and deliver it to them. I did end up going and delivering a couple of contracts for my supervisor though. Risk management starts in the contract stage and continues throughout the rest of the project. Ethical issues exist everywhere you look in the construction industry. One of the most common issues is bid shopping. Another issue that exists is companies following what the contract says. Along with that there is the issue of the contract language. There are times when the language of the contract can be interpreted in multiple ways. The General Contractor can interpret it in one way and management can interpret it in another
In design and build procurement, the design quality is not the key consideration. According to (Designingbuildingscouk, 2018), the ability to satisfy the client of this procurement is variable due to client less input into the detailed design or the contractor has insufficient experience of the process, therefore producing a low-quality product. In this project, this procurement cannot be chosen because Mr. Alexander is concerned about the quality of the products, so he wishes for someone to help him supervise and coordinate with the different work package contractors to control the quality of the
The Tender and Contract division of the project would also be taken upon. The contract is a mutual assent by two or more firms/persons, one making an offer and other accepting it. The details which go inside the formulation of a contract would be studied alongside the clauses which bind the parties involved from doing things correctly or to refrain them from doing things
Runwal Group is one of the legendary names in the world of construction in Mumbai since 1978 . It is the top greatest realty player in Mumbai Real Estate setting landmarks into the industry. The Group is delightfully addressed to as the large brand, became widely successful in the business by giving an exceptional quality with an advanced facilities in their each projects. Runwal has constructed several residential project but has felt their impact in the market and as well in the mind of the people looking for desired homes. Recently, they have announced the pre-launch of its most awaited project RUNWAL EIRENE, welcoming you to life past your expectations and desires. Runwal Eirene is the new tower soon will be constructed inside the most stunning residential project Runwal Garden City. The venture, Eirene is remarkably sprawls across 9 acres of land of place where there is scene of rich lavish green that is known for luscious green zone offers luxury and huge lifestyle. Runwal Eirene is the house that are developed by builder, yet the affection filled homes are constructed by each living souls. Runwal Eirene is brilliantly designed home and relish in its incredible lifestyle solaces. Runwal Eirene is the 4th Phase of the most prestigious project Garden City, this beautiful project is extremely nestled in the hotspot of Mumbai in the quietest part of Balkum, Thane (West), which is known to be the most prized region with all extraordinary planning. The locality Thane, is partnered by the three vital big avenues, especially National Highway 8 & 4 and Eastern Express Highway. Making you feel happy in living with...
When selecting vendors, the most important factors to consider are the quality, reliability, capability, financial stability, quality of materials of services provided and the risk involved working with a particular vendor.
One of the main feature of Navi Mumbai that should be highly focused is its housing. Without any doubt, housing plays a crucial role in overall increase of human life standards. It is not new that urban areas are consistently exploding with the rapid growth of citizens. Thus the government of India decided to build houses that could be affordable for population. The main instrument how to achieve this was to apply subsidization. With the advent of Navi Mumbai, there have been constructed over 122,000 of different types of accommodation. Half of them belong to lower income group. If to talk about the division of housing in Navi Mumbai, it should be mentioned two types, such as formal and non formal sectors. To the formal houses it can be referred private houses, co-operative houses, individual houses, and various sites for employees and poor people. Non formal sector mainly includes urban village, traditionally housing, and squatter nodes.
Delays on construction projects are a universal phenomenon. They are almost always accompanied by cost and time overruns. Construction project delays have a debilitating effect on parties (owner, contractor, and consultant) to a contract in terms of a growth in adversarial relationships, distrust, litigation, arbitration, cash-flow problems, and a general feeling of apprehension towards each other.
(hazreeni,azam, 2010). In the process, by using the conventional method of construction the project is a first choice from many small contractors are reluctant to adopt IBS system. It may the small contrctor was using conventional method compared the new method. (Kamar, Alshnawi, and hamid, 1779). It may financial issues become the main obstacle for small contractors to move forward with the IBS system (Kamar, Alshnawi, and hamid, 1779). This because of the structure of IBS is highest cost.
In general, there are different types of procurement type for various situations due to no one method can be suitable under the all different construction project. In this case, there are four procurement paths, which are traditional, design and build, management and design and manage, will be advised to use. However, each method has different aspects of advantages and disadvantages.
Green buildings need an approach including consideration towards health and wellbeing of the occupants in every aspects of the build projects, not only for the individual apartment unit but for the entire building, based on a wider context about the environment and the community around. This matter can be a huge approach which need an integrated thinking for the architects, designers, developers and government who is responsible in the community planning (Plass N 2007). Even though we are still in early stage, building a sustainable building nowadays is an establish concept with increasing rate of demand in most countries where it is supported by government in Europe, America, China, Hong Kong, Japan, and Korea. These government have been promoted by their respective Green Building Councils. In a rate where ages is threatened by the climate nowadays, there is an increasing demand for energy and resource efficient building, but there is also a need to build a healthy and comfortable homes that is not affected by undue emissions of harmful substances (Yu CWF 2010), glare (PR 2010) or insufficient lighting (Lim HS 2010), noise (Han MH 2010), hot and cold climate (Daghigh R 2009), where occupants can actually feel safe, can interact with each other freely and can build hope for our future. For commercial buildings, there are reports of evidence about the environmentally certified buildings are raising in the aspects of personal control, day lighting, thermal comfort, air quality and noise reduction which can increase the productivity of individuals in order for them to do work or business operation (Lee YS 20...
Due to the growth of population, the land man ratio has increased. And some problems have increased. Problems could be defined as needs of society. Hence the architecture also has changed in the individual form of the housing as well as composition in overall planning context.