Hoover Dam Research Paper

1440 Words3 Pages

The Hoover Dam is an engineering marvel completed in the year 1935. The dam spans the Colorado River in the Black Canyon, about 30 miles south of Las Vegas. The dam provides hydroelectric power and irrigation in the arid regions of Arizona and California. At the time, it was the tallest dam in the world and it created the largest man made lake in the United States. The dam was built before the luxuries of modern tools and technology, so the workers faced many challenges during the construction. The Hoover dam has an intriguing history, a difficult construction, and used revolutionary technology.

The Hoover Dam has a very intriguing beginning. In 1922, the Reclamation Service gave a report requesting for a dam to be built on the Colorado …show more content…

First, seven states had to approve of the construction. After a while of debate, it was approved by the Colorado River Compact. Next, the dam had to be approved by Congress. The opposing congressmen had a strong argument. They thought that it would only benefit California and that safety could not be guaranteed for the people living downriver or working on the dam. Congress hired a board of engineers to review the idea, and they said it was possible. After voting in both houses, the bill passed. President Calvin Coolidge signed the bill, approving of the project. The Hoover Dam was given $165 million to be built, along with two smaller dams …show more content…

The dam could not be poured in a single pour due to its size, so the engineers had to think of a different method. They decided to pour the concrete in five foot high forms of varying widths, which were stacked together. Each form had multiple 1 inch steel pipes in it, totaling to 582 miles of pipe. These pipes had cool water pumped through them to speed up the curing process. The base of the dam alone needed 230 individual blocks of concrete. The blocks were stacked with alternating schemes to add to the strength. Once the block of concrete was poured and cured, the pipes were filled with grout to add extra support. Grout was also poured in between the blocks of concrete.

Huge steel buckets carried the concrete to the designated form. They were seven feet high by seven feet wide, and weighed twenty tons. The buckets were suspended over the canyon with steel cables, and lowered to the correct form on the dam. Then, the bottom opened up, dumping the concrete into the form. The buckets were delivered once every 78 seconds, which kept everybody very busy. The workers then stirred it into the form. The dam used a total of 3,250,000 cubic yards of concrete before the dam was finished in

More about Hoover Dam Research Paper

Open Document